Project Progress
Public Works
Johns Creek, GA 30097
View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.
Jones Bridge Road Widening (Waters Road to State Bridge Road)
Latest update (Nov. 1, 2024)
Crews are working on traffic signal upgrades and pouring medians along the roadway. Grading and sidewalk installation is near completion toward the southern end of the project at Waters Road. Signal upgrades and sound abatement fencing installation will continue over the next few weeks.
The project is expected to be complete in summer 2025.
Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)
Latest Update (Oct. 25, 2024)
Crews have started repair and rehabilitation of an existing culvert under the roadway near the entrance to The Standard Club. Utility relocation is underway and the contractor continues grading operations. Storm drain installation will begin next week.
Construction is expected to be completed in spring 2027.
Town Center Stream Restoration & Multi-Use Trail
Latest update (July 19, 2024)
Clearing has begun for the Town Center Stream Restoration and multi-use trail project, which restores more than 1,500 linear feet of eroded streambank, and adds a multi-use, 10-foot wide ADA-compliant trail connecting McGinnis Ferry Road to Creekside Park.
The existing entrance to the sidewalk along East Johns Crossing is closed. Pedestrians should use caution near the construction barriers. In the next few weeks, crews will begin grading once clearing is complete.
The stream restoration project is expected to be completed in the winter.
Rogers Bridge Road Trail & Bell Road Trail
Latest Update (Nov. 15 2024)
Utility relocation work has been completed and grading work continues for the Rogers Bridge Road and Bell Road trail connection project.
Storm drainpipe installation will begin along Bell Road in the coming weeks and once completed, that portion of the trail will be installed. The project is expected to be complete in summer 2025.
Buice Road Trail (Spruill Road to Haverhill Lane)
Latest Update (Nov. 9, 2024)
Crews have begun installing the water line along the project route. Fill dirt will be added to level the project path and in the next few weeks, crews will begin to install retaining walls.
The project is expected to be completed in spring 2025.
Sargent Road at Ashwick Place Roundabout
Project Completed: October 2024
The Sargent Road at Ashwick Place roundabout project is now complete. City Council member Larry DiBiase and City staff marked the project’s completion with a ribbon cutting ceremony on Wednesday.
The project, which addressed safety concerns at the intersection of Sargent Road and Ashwick Place, included the installation of a roundabout and pedestrian improvements including crosswalks.
Medlock Bridge Road Intersection Improvements (Skyway Drive to Bell Road)
Project Completed: June 2024
City staff marked the completion of the Medlock Bridge Road improvement project with a ribbon cutting ceremony this week.
The project included included restriping the roadway to add a third lane in both directions from Bell Road to Skyway Drive, which helps alleviate traffic congestion and improve pedestrian connectivity in the area.
The improvement also included the installation of sidewalks and traffic signal reconfiguration.
Old Alabama Road Trail & Bike Lane
Project Completed: April 2024
The Old Alabama Road Trail & Bike Lane project is now complete. The project includes a trail along Old Alabama Road from Autrey Mill Road to Spruill Road. It also includes the addition of a four-foot bike lane along the roadway and a right-turn lane for motorists turning from Spruill Road onto Old Alabama Road.
Barnwell Road at Holcomb Bridge Road Intersection Improvements
Project Completed: April 2024
The Barnwell Road at Holcomb Bridge Road intersection improvement project has been completed with the sidewalk and pedestrian bridge open for use.
The project includes the addition of turn lanes, reshaping and regrading of the intersection to help traffic flow, and enhanced pedestrian connectivity.
Jones Bridge Road Trail & Bike Lane
Project Completed: March 2024
The project included the installation of a trail and bike lane along the roadway between Douglas Road and McGinnis Ferry Road. The project connects to the existing sidewalk and provides a connected corridor along Jones Bridge Road.
Medlock Bridge Road at Johns Creek Parkway Intersection Improvement
Project Completed: March 2024
As one of the intersection gateways leading into the Johns Creek Town Center area, the project included a sidewalk connection along the east side of Medlock Bridge Road from bell Road to Johns Creek Parkway and the addition of a through right-turn lane from northbound Medlock Bridge Road onto eastbound Johns Creek Parkway.
Buice Road Sidewalk
Project Completed: June 2024
The Buice Road sidewalk project has been completed. The project, which filled a pedestrian connectivity gap along the northern side of Buice Road between Twingate Drive and Kingston Crossing Circle, also included a substantial stormwater drainage upgrade.
This project is adding to the more than 96 miles of sidewalks and trails in Johns Creek and serves as an important community connection. As an emerging leader in health, wellness, and innovation, Johns Creek continues to implement opportunities for incorporating a healthy lifestyle and improved quality of life in our community.
Two additional sidewalk gaps along Buice Road (one over the Buice Road bridge and one from Spruill Road to Johns Creek) are in the right-of-way phase.