How can we help you?

Public Works

678-512-3200 11360 Lakefield Drive
Johns Creek, GA 30097

View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.

Jones Bridge Road Widening (Waters Road to State Bridge Road)

Latest update (Aug. 2, 2024)

Crews have shifted traffic lanes along Jones Bridge Road as part of the road widening project from Waters Road to State Bridge Road. Motorists can expect intermittent lane closures from 9 a.m. to 4 p.m. Monday – Friday, weather permitting. Please use caution in the area.

The driveways into and out of Dolvin Elementary School have been paved and are ready for the start of the school year. In the next few weeks, crews will install concrete barriers along the roadway to prepare for the installation of underground stormwater facilities.

The road widening project will provide a three-lane roadway with deceleration lanes into neighborhoods and improved egress from neighborhoods where appropriate. It also will provide longer carpool queuing lines and school bus lines at Dolvin Elementary which will remove more of the school traffic from the main travel lanes thus decreasing congestion.

The project, expected to be completed in summer 2025, addresses pedestrian safety and access with a sidewalk on one side of the road and a wider trail on the other side of the road.


Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)

Latest Update (Aug. 16, 2024)

IMG 0008 copy
Crews are working on clearing and erosion control.

Motorists can expect intermittent lane closures next week (Monday, Aug. 19 – Friday, Aug. 23) along Abbotts Bridge Road between Abbotts Walk Drive and Abbotts Run Trail as crews continue clearing and work on erosion control in the project area. Traffic control measures will be in place.

In the next few weeks, Sawnee EMC will begin to relocate power poles starting near Parsons Road and Abbotts Hill Elementary School.

Construction is expected to be completed in spring 2027.


Town Center Stream Restoration & Multi-Use Trail

Latest update (July 19, 2024)

Town Center stream restoration project
Crews are beginning to clear the area for the stream restoration and trail project.

Clearing has begun for the Town Center Stream Restoration and multi-use trail project, which restores more than 1,500 linear feet of eroded streambank, and adds a multi-use, 10-foot wide ADA-compliant trail connecting McGinnis Ferry Road to Creekside Park.

The existing entrance to the sidewalk along East Johns Crossing is closed. Pedestrians should use caution near the construction barriers. In the next few weeks, crews will begin grading once clearing is complete.

The stream restoration project is expected to be completed in the winter.


Rogers Bridge Road Trail & Bell Road Trail

Latest Update (Aug. 23, 2024)

Trail connections are underway along Rogers Bridge Road and Bell Road, making it easier for pedestrians to easily access nearby schools and Cauley Creek Park.

Crews are milling the existing roadway at the intersection of Rogers Bridge and Bell Road, which will help alleviate sight distance issues at the current elevation. Following milling, the area will be graded.

The project includes the installation of multi-use trails along the east side of Rogers Bridge Road from Bell Road to Amberleigh Way and along Bell Road from Cauley Creek Park to Rogers Bridge Road.

The intersection of Rogers Bridge Road and Bell Road will also be realigned and lowered about five feet to improve sight distance for drivers turning onto Bell Road and increase overall driver and pedestrian safety.

Detour Alert: Rogers Bridge Road is CLOSED between Bell Road and Kemper Drive while crews install stormwater lines and begin to realign the roadway as part of the Rogers Bridge trail project installation.

Rogers Bridge Road is open to local traffic only. Access to the neighborhoods along Rogers Bridge Road from McGinnis Road will be maintained at all times. The closure is expected to last approximately three months, weather permitting.

Bell Road and McGinnis Ferry Road will remain accessible to motorists.


Sargent Road at Ashwick Place Roundabout

Latest Update (Sept. 6, 2024)

Crews have installed the roundabout and medians along the roadway. Sod, landscaping, striping, and additional signage will be installed next week.

The project is expected to be completed ahead of schedule this fall.

Buice Road Trail (Spruill Road to Haverhill Lane)

Latest Update (Sept. 13, 2024)

IMG 0289 copy
Crews are clearing the project area and relocation of utilities begins in the coming weeks.

Crews have started clearing in the project area and silt fence installation is underway this week. Tree trimming is expected to be completed by next week, weather permitting. Relocation of utilities including the water lines will start next week.

The project is expected to be completed in spring 2025.


Buice Road Trail (Spruill Road to Haverhill Lane)

Buice Road trail groundbreaking
The City broke ground on the trail project in August 2024.

The Buice Road trail project is underway, which includes a 10-foot multi-use trail along the south side of Buice Road from Spruill Road to Haverhill Lane. The project will fill one of the remaining gaps along the road to complete a pedestrian corridor from Old Alabama Road to Jones Bridge Road.

The trail is expected to be completed in spring 2025.


Medlock Bridge Road Intersection Improvements (Skyway Drive to Bell Road)

Project Completed: June 2024

City staff marked the completion of the Medlock Bridge Road improvement project with a ribbon cutting ceremony this week.

The project included included restriping the roadway to add a third lane in both directions from Bell Road to Skyway Drive, which helps alleviate traffic congestion and improve pedestrian connectivity in the area.

The improvement also included the installation of sidewalks and traffic signal reconfiguration.


Old Alabama Road Trail & Bike Lane

Project Completed: April 2024

The Old Alabama Road Trail & Bike Lane project is now complete. The project includes a trail along Old Alabama Road from Autrey Mill Road to Spruill Road. It also includes the addition of a four-foot bike lane along the roadway and a right-turn lane for motorists turning from Spruill Road onto Old Alabama Road.


Barnwell Road at Holcomb Bridge Road Intersection Improvements

Project Completed: April 2024

The Barnwell Road at Holcomb Bridge Road intersection improvement project has been completed with the sidewalk and pedestrian bridge open for use.

The project includes the addition of turn lanes, reshaping and regrading of the intersection to help traffic flow, and enhanced pedestrian connectivity.


Jones Bridge Road Trail & Bike Lane

Project Completed: March 2024

The project included the installation of a trail and bike lane along the roadway between Douglas Road and McGinnis Ferry Road. The project connects to the existing sidewalk and provides a connected corridor along Jones Bridge Road.


Medlock Bridge Road at Johns Creek Parkway Intersection Improvement

Project Completed: March 2024

As one of the intersection gateways leading into the Johns Creek Town Center area, the project included a sidewalk connection along the east side of Medlock Bridge Road from bell Road to Johns Creek Parkway and the addition of a through right-turn lane from northbound Medlock Bridge Road onto eastbound Johns Creek Parkway.


Buice Road Sidewalk

Project Completed: June 2024

IMG 9401 copy
The Buice Road sidewalk project has been completed.

The Buice Road sidewalk project has been completed. The project, which filled a pedestrian connectivity gap along the northern side of Buice Road between Twingate Drive and Kingston Crossing Circle, also included a substantial stormwater drainage upgrade.

This project is adding to the more than 96 miles of sidewalks and trails in Johns Creek and serves as an important community connection. As an emerging leader in health, wellness, and innovation, Johns Creek continues to implement opportunities for incorporating a healthy lifestyle and improved quality of life in our community.

Two additional sidewalk gaps along Buice Road (one over the Buice Road bridge and one from Spruill Road to Johns Creek) are in the right-of-way phase.