
Project Progress
Public Works
Johns Creek, GA 30097
View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.
Jones Bridge Road Widening (Waters Road to State Bridge Road)

Latest update (May 2, 2025)
Sound abatement installation continues and stone veneer is being applied to the retaining walls. Crews are widening turn lanes in designated areas and asphalt, milling, and paving have begun along the project route. Following the installation of reinforced concrete pipe for stormwater management, crews will install curb, gutter, and sidewalk. After paving, crews will start place temporary striping on the roadway. Sod will be installed throughout the project.
The project is expected to be completed in summer 2025.
Jones Bridge Road at Douglas and Sargent roads
Latest update (April 26, 2025)
Curb and gutter have been poured along Jones Bridge Road past the intersection with Sargent Road. Portions of the trail have been poured to tie into the existing trail. Crews continue to replace utility poles in the project area and additional sections of the trail are being installed.
Construction is expected to be completed in summer 2025.
Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)
Latest Update (April 18 2025)
Bridge piles have been installed, bridge bents have been poured, and the rock embankments on either side of Johns Creek have been installed. Grading continues along the project corridor with several areas in the final stages of grading.
Utility relocations continue along the project route with electric utility poles being relocated. Installation of underground storm drains and structures, sewer lines, and water main lines continues. In the coming weeks, crews will continue work on the bridge including the delivery and installation of the bridge beams crossing Johns Creek. Utility relocation and grading will continue.
Construction is expected to be completed in spring 2027.
Medlock Bridge Road Pedestrian Crossing and Tunnel
Utility relocation is underway and is expected to be completed this spring.
The Medlock Bridge Road northbound and southbound lanes will shift toward the center median area from Johns Creek Parkway to East Johns Crossing beginning Monday, March 17 to prepare for the tunnel construction under the roadway. The speed limit will be reduced in the area from 45 mph to 35 mph. Motorists are advised to use caution in the area.
Construction is expected to be completed in fall 2025.
Town Center Stream Restoration & Multi-Use Trail
Project Completed: April 2025
The Town Center Stream Restoration & Trail project is now complete, following a ribbon cutting ceremony attended by City Council member Larry DiBiase, City staff, and project contractors.
The project restored more than 1,500 linear feet of eroded streambank and added a multi-use, 10-foot wide ADA-compliant trail connecting McGinnis Ferry Road to The Boardwalk at Town Center, the new park currently under construction adjacent to City Hall.
This addressed severe bank erosion, which contributed to heavy sediment loads to the entire Johns Creek watershed (including neighborhoods downstream of the Town Center area).
The project’s unique features include a combination of stormwater management techniques such as bioswales, regenerative stormwater conveyance structures, vegetated soil lifts, step pools, and other bioengineering practices. These elements not only improve the environmental health of the stream but also reduce pollutants downstream.
Rogers Bridge Road Trail & Bell Road Trail
Latest Update (Feb. 28, 2025)
The trail along Rogers Bridge Road is near completion. Crews are beginning to pour cement to create the trail along Bell Road and will be paving the right turn lane from Rogers Bridge Road onto Bell Road in the next couple of weeks.
The project is expected to be complete in summer 2025.
Buice Road Trail (Spruill Road to Haverhill Lane)
Latest Update (March 28, 2025)
The trail has been installed from Red Bird Lane to the Georgia Power entrance. Crews are installing the remaining stormwater drain pipes. Crews will begin grading and forming the rest of the curb, followed by installing more of the trail.
The project is expected to be completed in spring 2025.
Sargent Road at Ashwick Place Roundabout
Project Completed: October 2024
The Sargent Road at Ashwick Place roundabout project is now complete. City Council member Larry DiBiase and City staff marked the project’s completion with a ribbon cutting ceremony on Wednesday.
The project, which addressed safety concerns at the intersection of Sargent Road and Ashwick Place, included the installation of a roundabout and pedestrian improvements including crosswalks.
Medlock Bridge Road Intersection Improvements (Skyway Drive to Bell Road)
Project Completed: June 2024
City staff marked the completion of the Medlock Bridge Road improvement project with a ribbon cutting ceremony this week.
The project included included restriping the roadway to add a third lane in both directions from Bell Road to Skyway Drive, which helps alleviate traffic congestion and improve pedestrian connectivity in the area.
The improvement also included the installation of sidewalks and traffic signal reconfiguration.
Old Alabama Road Trail & Bike Lane
Project Completed: April 2024
The Old Alabama Road Trail & Bike Lane project is now complete. The project includes a trail along Old Alabama Road from Autrey Mill Road to Spruill Road. It also includes the addition of a four-foot bike lane along the roadway and a right-turn lane for motorists turning from Spruill Road onto Old Alabama Road.
Barnwell Road at Holcomb Bridge Road Intersection Improvements
Project Completed: April 2024
The Barnwell Road at Holcomb Bridge Road intersection improvement project has been completed with the sidewalk and pedestrian bridge open for use.
The project includes the addition of turn lanes, reshaping and regrading of the intersection to help traffic flow, and enhanced pedestrian connectivity.
Jones Bridge Road Trail & Bike Lane
Project Completed: March 2024
The project included the installation of a trail and bike lane along the roadway between Douglas Road and McGinnis Ferry Road. The project connects to the existing sidewalk and provides a connected corridor along Jones Bridge Road.
Medlock Bridge Road at Johns Creek Parkway Intersection Improvement
Project Completed: March 2024
As one of the intersection gateways leading into the Johns Creek Town Center area, the project included a sidewalk connection along the east side of Medlock Bridge Road from bell Road to Johns Creek Parkway and the addition of a through right-turn lane from northbound Medlock Bridge Road onto eastbound Johns Creek Parkway.
Buice Road Sidewalk
Project Completed: June 2024
The Buice Road sidewalk project has been completed. The project, which filled a pedestrian connectivity gap along the northern side of Buice Road between Twingate Drive and Kingston Crossing Circle, also included a substantial stormwater drainage upgrade.
This project is adding to the more than 96 miles of sidewalks and trails in Johns Creek and serves as an important community connection. As an emerging leader in health, wellness, and innovation, Johns Creek continues to implement opportunities for incorporating a healthy lifestyle and improved quality of life in our community.
Two additional sidewalk gaps along Buice Road (one over the Buice Road bridge and one from Spruill Road to Johns Creek) are in the right-of-way phase.