How can we help you?

Public Works

678-512-3200 11360 Lakefield Drive
Johns Creek, GA 30097

View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.


Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)

Latest Update (Feb. 13, 2026)

2026AbbottsBridge DSC03914 copy
Work continues on the retaining wall at the curve.

This week, crews took advantage of warmer temperatures to continue retaining wall installations and asphalt paving in preparation for the traffic shift in the next month, weather permitting. In addition, crews began forming and pouring additional trail sections across from Abbotts Hill Elementary School.

Construction is expected to be completed in spring 2027.


Barnwell Road Corridor Improvements

Latest Update: Feb. 20, 2026

IMG 2736
Crews have completed clearing and are installing silt fence along the project route.

Crews have completed clearing and are installing silt fence along the project route. Utility relocations will begin after erosion control measures are in place.

Construction is expected to be completed in spring 2027.


Buice Road Bridge Replacement

Latest update (Feb. 27, 2026)

BuiceRd Detour

Buice Road will be closed to through traffic at the bridge over Johns Creek beginning Monday, March 9. Motorists are advised to use Spruill Road and Old Alabama Road as alternate routes.

Crews are completing the gas line installation along the project route. AT&T will relocate utilities in the next few weeks.

Construction is anticipated to be completed in fall 2026.


Johns Creek Parkway

Latest Update: March 6, 2026

Crews have completed the demolition of existing sidewalk structures, curbs, and gutters, and have constructed more than 700 linear feet of curb and gutter as well as storm drainage installation at East Johns Crossing.
A major milestone has been reached at East Johns Crossing with the excavation and forming of signal pole foundation footings, an important step toward the installation of the new traffic signal. This month, work includes the installation of new sidewalks, curb and gutter, and signal poles. Additional work will include demolition of the Johns Creek Parkway and Lakefield Drive intersection and raising the roadway to improve the overall intersection.

Construction is expected to be completed in the summer.


Jones Bridge Road at Douglas and Sargent roads

Latest update (Feb. 6, 2026)

An aerial view of the Jones Bridge at Sargent and Douglas intersection.
Crews continue stormwater utility work.

Stormwater utilities are being installed at both intersections of Sargent and Douglas roads. Crews will begin installing poles and attaching utilities in the next few weeks.

Construction is expected to be completed in summer 2026.


McGinnis Ferry Road widening

Latest Update: Feb. 6, 2026

2025McGinnisFerryWidening DSC00049
Utilities, stormdrain pipe, and drainage structures continue to be installed.

Utilities, stormdrain pipe, and drainage structures continue to be installed for the McGinnis Ferry Road widening project.

Retaining wall construction has begun across from the Seven Oaks neighborhood and near Jones Bridge and McGinnis Ferry Road. Footers for additional retaining walls will be poured and clearing will begin near the intersection of McGinnis Ferry Road and Douglas Road.

Construction is expected to be completed in spring 2028.


Medlock Bridge Road Pedestrian Crossing and Tunnel

An aerial image of the pedestrian crossing and tunnel construction.
Crews have completed backfilling around the tunnel, finished grading around the walls, and poured asphalt on the roadway on the eastern side of the tunnel.

Latest Update (Jan. 15, 2026)

Crews have completed backfilling around the tunnel, finished grading around the walls, and poured asphalt on the roadway on the eastern side of the tunnel.

What’s Upcoming: The Medlock Bridge Road northbound and southbound lanes will shift toward the east side of Medlock Bridge Road from Johns Creek Parkway to East Johns Crossing beginning the week of Jan. 19 to prepare for work on the western side of the pedestrian crossing and tunnel under the roadway. The speed limit is reduced in the area from 45 mph to 35 mph. Motorists are advised to use caution in the area.

Timeline:

Construction is expected to be completed in the spring.


Rogers Bridge Road Trail & Bell Road Trail

Project Completed: September 2025

Another trail connection has been completed in Johns Creek, making it easier for pedestrians to easily access nearby schools and Cauley Creek Park.

The project included the installation of multi-use trails along the east side of Rogers Bridge Road from Bell Road to Amberleigh Way and along Bell Road from Cauley Creek Park to Rogers Bridge Road.

Another project component was the realignment of the intersection of Rogers Bridge Road and Bell Road. It was lowered about five feet to improve sight distance for drivers turning onto Bell Road and increase overall driver and pedestrian safety.


Jones Bridge Road Widening (Waters Road to State Bridge Road)

Project Completed (August 2025)

The Jones Bridge Road widening project is complete! New trees and landscape plants will be added separately in phases starting in October.

Mayor John Bradberry, Mayor Pro Tem Dilip Tunki, Rep. Scott Hilton, Fulton County School Board Member Kristin McCabe, Fulton County Schools Area Superintendent Brian Downey, Dolvin Elementary School Principal Andy Stein, a group of Dolvin students, and City staff gathered to mark the project’s completion.

The project, from Waters Road to State Bridge Road, adds deceleration lanes into neighborhoods and improves egress from neighborhoods where appropriate. Some areas along the roadway were repurposed into bike lanes.

The project also provides longer carpool queuing lines and school bus lines at Dolvin Elementary which removes more of the school traffic from the main travel lanes thus decreasing congestion.

It also addresses pedestrian safety and access with a sidewalk on one side of the road and a wider trail on the other side of the road.

The project has a few punch-list and clean-up items, including the sound abatement fencing, remaining to be completed by the end of September.


Buice Road Trail (Spruill Road to Haverhill Lane)

Project Completed: July 2025

2025BuiceRdTrailRibbonCutting DSC00482 copy
The Buice Road trail is now complete.

The Buice Road Trail project is officially complete, marking a significant step in strengthening neighborhood connectivity and enhancing pedestrian safety in our community.

The project, which included a 10-foot multi-use trail along the south side of Buice Road, fills one of the remaining gaps along the road to complete a pedestrian corridor from Old Alabama Road to Jones Bridge Road.


Town Center Stream Restoration & Multi-Use Trail

Town center stream restoration ribbon cutting
The Town Center Stream Restoration & Trail project is now complete, following a ribbon cutting ceremony.

Project Completed: April 2025

The Town Center Stream Restoration & Trail project is now complete, following a ribbon cutting ceremony attended by City Council member Larry DiBiase, City staff, and project contractors.

The project restored more than 1,500 linear feet of eroded streambank and added a multi-use, 10-foot wide ADA-compliant trail connecting McGinnis Ferry Road to The Boardwalk at Town Center, the new park currently under construction adjacent to City Hall.

This addressed severe bank erosion, which contributed to heavy sediment loads to the entire Johns Creek watershed (including neighborhoods downstream of the Town Center area).

The project’s unique features include a combination of stormwater management techniques such as bioswales, regenerative stormwater conveyance structures, vegetated soil lifts, step pools, and other bioengineering practices. These elements not only improve the environmental health of the stream but also reduce pollutants downstream.