Project Progress
Public Works
Johns Creek, GA 30097
View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.
Jones Bridge Road Widening (Waters Road to State Bridge Road)
Latest update (Nov. 1, 2024)
Crews are working on traffic signal upgrades and pouring medians along the roadway. Grading and sidewalk installation is near completion toward the southern end of the project at Waters Road. Signal upgrades and sound abatement fencing installation will continue over the next few weeks.
The project is expected to be complete in summer 2025.
Jones Bridge Road at Douglas and Sargent roads
Latest update (Dec. 13, 2024)
Crews continue the realignment of Douglas Road and the installation of the stormwater infrastructure as part of the Jones Bridge Road at Douglas and Sargent roads improvement project.
Crews will work on constructing retaining walls and continue the installation of the trail on Jones Bridge Road to tie into the existing trail in the next few weeks.
Construction is expected to be completed in summer 2025.
Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)
Latest Update (Dec. 21, 2024)
Crews installed filter fabric and stone bridging for the new road alignment and poured concrete walls for culvert repairs. Work continues with installing underground pipe for stormwater and removing the rock hill to accommodate the new road alignment.
Construction is expected to be completed in spring 2027.
Town Center Stream Restoration & Multi-Use Trail
Latest update (Nov. 22, 2024)
Crews are working on the final grading for the trail installation starting near McGinnis Ferry Road.
Concrete work and landscaping are scheduled to begin next week. The last remaining stone structures toward East Johns Crossing will be installed in the next few weeks.
The stream restoration project is expected to be completed in the winter.
Rogers Bridge Road Trail & Bell Road Trail
Latest Update (Dec. 27, 2024)
Asphalt installation has been completed and temporary striping is in place at the Rogers Bridge Road and Bell Road intersection as part of the trail installation project along both roadways.
The intersection of Rogers Bridge Road and Bell Road has been realigned and lowered about five feet to improve sight distance for drivers turning onto Bell Road and increase overall driver and pedestrian safety.
Crews will continue installing two residential driveways after the new year so the remainder of the trail can be installed on Rogers Bridge Road. In the coming weeks, crews will install the Bell Road trail.
The project is expected to be complete in summer 2025.
Buice Road Trail (Spruill Road to Haverhill Lane)
Latest Update (Jan. 3, 2025)
Water lines have been installed and crews are placing reinforced concrete pipes for stormwater along the project route. In the coming weeks, the retaining wall will be constructed and crews will grade the area to prepare for the new sidewalk.
The project is expected to be completed in spring 2025.
Sargent Road at Ashwick Place Roundabout
Project Completed: October 2024
The Sargent Road at Ashwick Place roundabout project is now complete. City Council member Larry DiBiase and City staff marked the project’s completion with a ribbon cutting ceremony on Wednesday.
The project, which addressed safety concerns at the intersection of Sargent Road and Ashwick Place, included the installation of a roundabout and pedestrian improvements including crosswalks.
Medlock Bridge Road Intersection Improvements (Skyway Drive to Bell Road)
Project Completed: June 2024
City staff marked the completion of the Medlock Bridge Road improvement project with a ribbon cutting ceremony this week.
The project included included restriping the roadway to add a third lane in both directions from Bell Road to Skyway Drive, which helps alleviate traffic congestion and improve pedestrian connectivity in the area.
The improvement also included the installation of sidewalks and traffic signal reconfiguration.
Old Alabama Road Trail & Bike Lane
Project Completed: April 2024
The Old Alabama Road Trail & Bike Lane project is now complete. The project includes a trail along Old Alabama Road from Autrey Mill Road to Spruill Road. It also includes the addition of a four-foot bike lane along the roadway and a right-turn lane for motorists turning from Spruill Road onto Old Alabama Road.
Barnwell Road at Holcomb Bridge Road Intersection Improvements
Project Completed: April 2024
The Barnwell Road at Holcomb Bridge Road intersection improvement project has been completed with the sidewalk and pedestrian bridge open for use.
The project includes the addition of turn lanes, reshaping and regrading of the intersection to help traffic flow, and enhanced pedestrian connectivity.
Jones Bridge Road Trail & Bike Lane
Project Completed: March 2024
The project included the installation of a trail and bike lane along the roadway between Douglas Road and McGinnis Ferry Road. The project connects to the existing sidewalk and provides a connected corridor along Jones Bridge Road.
Medlock Bridge Road at Johns Creek Parkway Intersection Improvement
Project Completed: March 2024
As one of the intersection gateways leading into the Johns Creek Town Center area, the project included a sidewalk connection along the east side of Medlock Bridge Road from bell Road to Johns Creek Parkway and the addition of a through right-turn lane from northbound Medlock Bridge Road onto eastbound Johns Creek Parkway.
Buice Road Sidewalk
Project Completed: June 2024
The Buice Road sidewalk project has been completed. The project, which filled a pedestrian connectivity gap along the northern side of Buice Road between Twingate Drive and Kingston Crossing Circle, also included a substantial stormwater drainage upgrade.
This project is adding to the more than 96 miles of sidewalks and trails in Johns Creek and serves as an important community connection. As an emerging leader in health, wellness, and innovation, Johns Creek continues to implement opportunities for incorporating a healthy lifestyle and improved quality of life in our community.
Two additional sidewalk gaps along Buice Road (one over the Buice Road bridge and one from Spruill Road to Johns Creek) are in the right-of-way phase.