How can we help you?

Public Works

678-512-3200 11360 Lakefield Drive
Johns Creek, GA 30097

View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.

Jones Bridge Road Widening (Waters Road to State Bridge Road)

Latest update (Jan. 24, 2025)

Crews are currently placing grading material in front of The Orchards neighborhood to prepare for sod installation. Crews are also working on the traffic signals along Jones Bridge Road at the Waters Road, Buice Road, and Morton Road intersections.

The new roadway is being prepared for asphalt in the next month. Median islands and stormwater drains will continue to be installed along the project route. Sound abatement fencing installation continues next week.

The project is expected to be complete in summer 2025.


Jones Bridge Road at Douglas and Sargent roads

Latest update (Dec. 13, 2024)

Workers installing sidewalk along Jones Bridge Road
Crews are installing the stormwater infrastructure along the roadway.

Crews continue the realignment of Douglas Road and the installation of the stormwater infrastructure as part of the Jones Bridge Road at Douglas and Sargent roads improvement project.

Crews will work on constructing retaining walls and continue the installation of the trail on Jones Bridge Road to tie into the existing trail in the next few weeks.

Construction is expected to be completed in summer 2025.


Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)

Latest Update (Jan. 31, 2025)

 DSC3806
The contractor is installing storm drain structures, water line, and sewer throughout the project route.

The contractor is installing storm drain structures, water line, and sewer throughout the project route. Phase one of utility relocation is underway and is expected to be completed in the next few weeks, weather permitting.
Excavation of the large hill is underway and expected to be completed next month. Crews will begin installing a new culvert and pouring retaining walls and the bridge foundation in February and March.

Construction is expected to be completed in spring 2027.


Town Center Stream Restoration & Multi-Use Trail

Latest update (Jan. 17, 2025)

DCIM105MEDIADJI 0917.JPG
Crews are working on installing the final landscaping on the project site.

Crews are currently working on installing final landscaping throughout the Town Center Stream Restoration and Trail project. Following the relocation of a sprinkler line last week, the last portion of the trail will be poured in the coming weeks.

The stream restoration project is expected to be completed in the spring.


Rogers Bridge Road Trail & Bell Road Trail

Latest Update (Feb. 28, 2025)

The trail along Rogers Bridge Road is near completion. Crews are beginning to pour cement to create the trail along Bell Road and will be paving the right turn lane from Rogers Bridge Road onto Bell Road in the next couple of weeks.

The project is expected to be complete in summer 2025.


Buice Road Trail (Spruill Road to Haverhill Lane)

Latest Update (Feb. 7, 2025)

Default
Reinforced concrete pipe is being installed and the water line installation has been completed.

Reinforced concrete pipe is being installed and the water line installation has been completed. Crews will begin building the retaining wall near Spruill Road. Curb and gutter will be poured in the next few weeks followed by the trail construction.

The project is expected to be completed in spring 2025.


Sargent Road at Ashwick Place Roundabout

Project Completed: October 2024

The Sargent Road at Ashwick Place roundabout project is now complete. City Council member Larry DiBiase and City staff marked the project’s completion with a ribbon cutting ceremony on Wednesday.

The project, which addressed safety concerns at the intersection of Sargent Road and Ashwick Place, included the installation of a roundabout and pedestrian improvements including crosswalks.


Medlock Bridge Road Intersection Improvements (Skyway Drive to Bell Road)

Project Completed: June 2024

City staff marked the completion of the Medlock Bridge Road improvement project with a ribbon cutting ceremony this week.

The project included included restriping the roadway to add a third lane in both directions from Bell Road to Skyway Drive, which helps alleviate traffic congestion and improve pedestrian connectivity in the area.

The improvement also included the installation of sidewalks and traffic signal reconfiguration.


Old Alabama Road Trail & Bike Lane

Project Completed: April 2024

The Old Alabama Road Trail & Bike Lane project is now complete. The project includes a trail along Old Alabama Road from Autrey Mill Road to Spruill Road. It also includes the addition of a four-foot bike lane along the roadway and a right-turn lane for motorists turning from Spruill Road onto Old Alabama Road.


Barnwell Road at Holcomb Bridge Road Intersection Improvements

Project Completed: April 2024

The Barnwell Road at Holcomb Bridge Road intersection improvement project has been completed with the sidewalk and pedestrian bridge open for use.

The project includes the addition of turn lanes, reshaping and regrading of the intersection to help traffic flow, and enhanced pedestrian connectivity.


Jones Bridge Road Trail & Bike Lane

Project Completed: March 2024

The project included the installation of a trail and bike lane along the roadway between Douglas Road and McGinnis Ferry Road. The project connects to the existing sidewalk and provides a connected corridor along Jones Bridge Road.


Medlock Bridge Road at Johns Creek Parkway Intersection Improvement

Project Completed: March 2024

As one of the intersection gateways leading into the Johns Creek Town Center area, the project included a sidewalk connection along the east side of Medlock Bridge Road from bell Road to Johns Creek Parkway and the addition of a through right-turn lane from northbound Medlock Bridge Road onto eastbound Johns Creek Parkway.


Buice Road Sidewalk

Project Completed: June 2024

IMG 9401 copy
The Buice Road sidewalk project has been completed.

The Buice Road sidewalk project has been completed. The project, which filled a pedestrian connectivity gap along the northern side of Buice Road between Twingate Drive and Kingston Crossing Circle, also included a substantial stormwater drainage upgrade.

This project is adding to the more than 96 miles of sidewalks and trails in Johns Creek and serves as an important community connection. As an emerging leader in health, wellness, and innovation, Johns Creek continues to implement opportunities for incorporating a healthy lifestyle and improved quality of life in our community.

Two additional sidewalk gaps along Buice Road (one over the Buice Road bridge and one from Spruill Road to Johns Creek) are in the right-of-way phase.