How can we help you?

Public Works

678-512-3200 11360 Lakefield Drive
Johns Creek, GA 30097

View the latest updates on active construction projects in the City of Johns Creek. Subscribe for the City’s Construction Project Progress email notification.

Jones Bridge Road Widening (Waters Road to State Bridge Road)

Latest update (July 11, 2025)

Paving and temporary striping work has been completed. Crews will install signs, sound abatement, and sod, but the roadway is operating as it will upon completion.

The project is expected to be completed in summer 2025.


Jones Bridge Road at Douglas and Sargent roads

Latest update (April 26, 2025)

Jones bridge douglas sargent
Curb and gutter have been poured along Jones Bridge Road past the intersection with Sargent Road.

Curb and gutter have been poured along Jones Bridge Road past the intersection with Sargent Road. Portions of the trail have been poured to tie into the existing trail. Crews continue to replace utility poles in the project area and additional sections of the trail are being installed.

Construction is expected to be completed in summer 2025.


Abbotts Bridge Road improvements (Parsons Road to Medlock Bridge Road)

Latest Update (Aug. 8, 2025)

TC 00384 copy
Crews paved the road from Abbotts Hill Elementary to the bridge over Johns Creek as part of the road widening project. The bridge deck was poured with concrete last week.

Crews paved the road from Abbotts Hill Elementary to the bridge over Johns Creek as part of the road widening project. The bridge deck was poured with concrete last week.

Water main lines and retaining walls continue to be installed along the project route. The large hill has been cut back and crews will begin building the footer for the retaining wall at the bottom of the hill.

Construction is expected to be completed in spring 2027.


Medlock Bridge Road Pedestrian Crossing and Tunnel

Pedestrian tunnel construction along Medlock Bridge Road.
Traffic will shift along Medlock Bridge Road for the pedestrian tunnel construction.

Latest Update (July 18, 2025)

Utility relocation is underway and is expected to be completed this spring.

The Medlock Bridge Road northbound and southbound lanes will shift toward the center median area from Johns Creek Parkway to East Johns Crossing beginning Monday, March 17 to prepare for the tunnel construction under the roadway. The speed limit will be reduced in the area from 45 mph to 35 mph. Motorists are advised to use caution in the area.

Construction is expected to be completed in fall 2025.


Rogers Bridge Road Trail & Bell Road Trail

Latest Update (July 11, 2025)

The project, from Spruill Road to Haverhill Lane, has reached substantial completion with installation of the rock face on the retaining wall, signage and marking, and final grassing. Staff completed the final punch-list walk-through in late June and anticipate all punch-list items will be resolved in the next week. The trail is completed and open to pedestrian traffic.

The project is expected to be complete in summer 2025.


Buice Road Trail (Spruill Road to Haverhill Lane)

Project Completed: July 2025

2025BuiceRdTrailRibbonCutting DSC00482 copy
The Buice Road trail is now complete.

The Buice Road Trail project is officially complete, marking a significant step in strengthening neighborhood connectivity and enhancing pedestrian safety in our community.

The project, which included a 10-foot multi-use trail along the south side of Buice Road, fills one of the remaining gaps along the road to complete a pedestrian corridor from Old Alabama Road to Jones Bridge Road.


Town Center Stream Restoration & Multi-Use Trail

Town center stream restoration ribbon cutting
The Town Center Stream Restoration & Trail project is now complete, following a ribbon cutting ceremony.

Project Completed: April 2025

The Town Center Stream Restoration & Trail project is now complete, following a ribbon cutting ceremony attended by City Council member Larry DiBiase, City staff, and project contractors.

The project restored more than 1,500 linear feet of eroded streambank and added a multi-use, 10-foot wide ADA-compliant trail connecting McGinnis Ferry Road to The Boardwalk at Town Center, the new park currently under construction adjacent to City Hall.

This addressed severe bank erosion, which contributed to heavy sediment loads to the entire Johns Creek watershed (including neighborhoods downstream of the Town Center area).

The project’s unique features include a combination of stormwater management techniques such as bioswales, regenerative stormwater conveyance structures, vegetated soil lifts, step pools, and other bioengineering practices. These elements not only improve the environmental health of the stream but also reduce pollutants downstream.


Sargent Road at Ashwick Place Roundabout

Project Completed: October 2024

The Sargent Road at Ashwick Place roundabout project is now complete. City Council member Larry DiBiase and City staff marked the project’s completion with a ribbon cutting ceremony on Wednesday.

The project, which addressed safety concerns at the intersection of Sargent Road and Ashwick Place, included the installation of a roundabout and pedestrian improvements including crosswalks.