McGinnis Ferry Road - Phase 2

Project Current Phase:

Right of Way Phase

Map:
McGinnis Ferry Road

 

Where:

 Seven Oaks Parkway to Douglas Road

Why: 

Faster travel, less congestion

Who:

City of Johns Creek, Forsyth County, City of Alpharetta

When:

Construction anticipated in 2023
 

Current Issues:

  • Traffic congestion along corridor
  • Original design was to handle 12,390 vehicles/day; currently handles 19,177/day (55% over capacity)

Solution:

  • Widening from 2 to 4 lanes will accommodate a total of 35,820 cars/day
  • Project cost: $6.8 million (2021 estimate)
  • City to apply for state grants to go towards project costs

Anticipated Results:

  • Modeled widening project reduces delay by 58% or 4 minutes and 12 seconds per car
  • Project reduces 733 hours of delay each day (considering volume)